ecostattheader
Want to know your Score and save the Test ? Click Here
Kerala PWD Test - Paper II
Choose the correct answer from the following options
1. An item of work done by the contractor measured recorded and check measured by competent authorities was omitted to be included in the final bill. After the payment of the final bill the Executive Engineer has paid for this item finding it bonafide. Comment :
A Govt. sanction was necessary
B Action of the Executive Engineer is in order
C Chief Engineer's sanction was necessary
D Payment after the settlement of the final bill was not allowable